Guernsey Power Station – 1st Unit Restart Update
As previously communicated on November 27, 2023, the 1st unit was expected to restart on November 27, 2023, but restart was delayed. The unit is anticipated
Guernsey Power Station is a state-of-the-art facility designed to maximize power output with minimal impact on the surrounding environment. The plant uses combined-cycle technology consisting of both natural gas-powered turbines and steam powered turbines. The combined-cycle design captures the excess heat generated by the gas turbines and, rather than releasing that heat into the air, uses the excess heat to make steam to power the steam turbines. This advanced technology allows the plant to generate significantly more electricity – up to 50 percent more – from the same amount of fuel as a traditional plant.
Guernsey Power Station also uses dry cooling technology, reducing water usage by as much as 95 percent compared to traditional water-cooled plants. And because of its advanced design, it achieves the lowest possible air emissions – a benefit that will be amplified as greater reliance for power is placed on new, clean technology power plants like Guernsey Power Station.
As previously communicated on November 27, 2023, the 1st unit was expected to restart on November 27, 2023, but restart was delayed. The unit is anticipated
As previously communicated on November 27, 2023, the 1st unit was expected to restart on November 27, 2023, but restart was delayed. The unit is anticipated
As previously communicated on November 13, 2023, the 1st unit was shutdown normally for its normal fall maintenance outage. The outage is complete and the unit
As previously communicated on November 13, 2023, the 2nd unit was shutdown normally on November 4, 2023, for its normal fall maintenance outage. This normal fall
As previously communicated on November 16, 2023, the 3rd unit was actually started on November 19, 2023, which required the unit to be operated on bypass
As previously communicated on November 13, 2023, the 3rd unit normal fall outage was anticipated to be complete on or about November 18, 2023. The outage
Caithness Energy, L.L.C. (“Caithness“) is a privately-held Independent Power Producer specializing in the development, acquisition, operation and management of renewable energy and natural gas projects.
Guernsey Power Station LLC
c/o Caithness Services LLC
960 Holmdel Road
Building II, Floor 2
Holmdel, NJ 07733
Orion Strategies
Community Affairs: (740) 421-0378
Office: 212-921-9099
Fax: 212-921-9239
[email protected]