Over the next couple of days near final construction testing and commissioning activities of the Facility will occur which includes operating all three units at the same time for steam blows, a temporary construction configuration. This temporary three unit steam blow activity will produce the highest temporary sound levels and will be completed as quickly as possible.
Guernsey Power Station: Elevated Noise Event
One of the units at the station is returning from maintenance and will be starting through the night. There may be periods of increased noise