Guernsey Power Station Statement on Increased Sound Levels for Next 12-48 Hours

Commissioning activities at the Guernsey Power Station continue to progress towards completion.  Some of the remaining commissioning activities on two of three units will produce sound levels similar to steam blows, which, as has been communicated previously, steam blows produce significantly higher sound levels than normal operation. The two units producing the increased sound levels will be operated around the clock for the next 12-48 hours.   

We appreciate the patience and support of our neighbors and community and will continue to post related information on our website: www.guernseypowerstation.com

Current News

Guernsey Power Station – 3rd Unit Restart

As previously communicated on September 14, 2023, the 3rd unit mechanical repair is complete.  The unit will be restarted today, September 15, 2023, at approximately 4:00pm